Home /
Expert Answers /
Other /
draw-an-activity-on-node-network-diagram-representing-the-following-logical-relationships-calculate-
(Answered): Draw an activity-on-node network diagram representing the following logical relationships. Calculat ...
Draw an activity-on-node network diagram representing the following logical relationships. Calculate the early start, early finish, late start, late finish, and total float and identify these values on the diagram using the format described in lecture (and shown below). Identify the critical path. What is the minimal total project duration? 1. Activity on node notation: ES= EF= LS= LF= TF= Predecessors Duration Activity Successors Start A 0 ? Start ?,?,D 7 ? ? G 6 ? ? 5 E,F D ? 2 E C ? 13 F ? ?. 4 D,B 18 Finish ? ?,F 7 Finish F,G 5 Finish ?. 0